Assessing the Benefits and Challenges of Implementing 4D Modeling in Construction

https://doi.org/10.23947/2949-1835-2025-4-2-75-84

EDN: DTRROH

Abstract

Introduction. Improved visualization is one of the results of the implementation of information modeling technology. Information modeling technology was mainly used by designers when developing a digital 3D model of an object. 4D modeling combines the organizational and technological sequence of works in the project with a parametric digital 3D model of the object under construction. 4D modeling can potentially contribute to the effective implementation of the project, but data on the scale of 4D implementation are limited, there is no empirical data in practice on the possibilities and problems of using this technology. The purpose of the study is to study the state of implementation of 4D modeling, the advantages of use, the main problems that hinder effective implementation, as well as incentives for implementation in the construction sector.
Materials and Methods. The article used a qualitative analysis of the functionality of 4D modeling to form a questionnaire for a survey among specialists in the construction industry. Based on the analysis of the array of data obtained, a statistical analysis was carried out to identify key problems and incentives for the implementation of 4D modeling in the activities of construction organizations.
Results. The main reasons for the insufficient implementation of 4D modeling technology in construction organizations are identified along with high awareness of the benefits of use. Critical problems that hinder the implementation of this technology are identified, as well as key factors that can stimulate the implementation of investment and construction projects using 4D modeling.
Discussion and Conclusion. The results of the study provide a basis for theoretical analysis to solve the problems of implementing 4D modeling in the construction industry. The study uses the theory of sustainable development and the theory of the full life cycle as a theoretical basis, combines qualitative and quantitative research methods, and conducts an in-depth study of various factors that affect the management of investment and construction projects using 4D modeling technology.

About the Author

K. M. Kryukov
Don State Technical University
Russian Federation

Konstantin M. Kryukov, Cand. Sci. (Eng.), Associate Professor of the Department of Construction Management

1 Gagarin Square, Rostov-on-Don, 344003, Russian Federation



References

1. Stolbov IV Modern Approaches to the Integrated Implementation of Information Modeling Technologies at all Stages of the Life Cycle of a Capital Construction object /Real Estate Object. Science Prospects. 2023;165(6):108–113 (In Russ.) URL: https://moofrnk.com/assets/files/journals/science-prospects/165/science-prospect-6(165)-main.pdf (accessed 10.04.2025)

2. Bovteev SV Current State and Prospects for the Usage of 4D Modeling in the Sphere of Construction in the Russian Federation. Bulletin of Civil Engineers. 2023;97(2):65–74. (In Russ.) http://doi.org/10.23968/1999-5571-2023-20-2-65-74

3. Wang L, Lee J, Nimawat Ja. Integrated 4D Design Change Management Model for Construction Projects. Journal of Construction Engineering and Management - ASCE. 2024;150(5). http://doi.org/10.1061/jcemd4.coeng-14246

4. Nechiporchuk Y, Bashkova R Brief Overview of 4Dmodeling in Construction. Architecture. Construction. Education. 2020;15(1):35–41. (In Russ.) http://doi.org/10.18503/2309-7434-2020-1(15)-35-41

5. Pimenov SI Levels of Decomposition of Construction Digital information models (4 D models) for the Tasks of Organizational and Technological Modeling of Construction Production. News of Higher Educational Institutions. Construction. 2023;770(2):65–78. (In Russ.) http://doi.org/10.32683/0536-1052-2023-770-2-65-78

6. Swallow M, Zulu S. Benefits and Barriers to the Adoption of 4D Modeling for Site Health and Safety Management. Front. Built Environ. 2019;4:86. http://doi.org/10.3389/fbuil.2018.00086

7. Crowther J, Ajayi SO Impacts of 4D BIM on construction project performance. International Journal of Construction Management. 2021;21(7):724–737. http://doi.org/10.1080/15623599.2019.1580832

8. Doukari O, Seck B, Greenwood D. The efficient generation of 4D BIM construction schedules: A case study of the Nanterre 2 CESI project in France. Frontiers in Built Environment. 2022;8. http://doi.org/10.3389/fbuil.2022.998309

9. Shcherba NV, Kuzhin MF Optimization of Calendar and Resource Planning Using BIM Technologies in Industrial Construction. Construction Production. 2020;3:35–40. (In Russ.) http://doi.org/10.54950/26585340_2020_3_35

10. Gushchina YuV, Saushkin DA Optimization of construction calendar plans based on BIM modeling. Bulletin of the Volgograd State University of Architecture and Civil Engineering. Series: Construction and architecture. 2020;81(4):438–447. (In Russ.) URL: https://elibrary.ru/item.asp?id=44694133 (accessed: 10.04.2025).

11. Sharmanov VV, Romanovich MA, Simankina TL Management of the Construction Process Using a Digital Construction Organization Project. Engineering Journal of Don. 2024;111(3):678–695. (In Russ.) URL: https://cyberleninka.ru/article/n/upravlenie-protsessom-stroitelstva-s-pomoschyu-tsifrovogo-proekta-organizatsii-stroitelstva (accessed: 10.04.2025).

12. Biche-Ool HV Practical Application of 4D Modeling in Construction Organizations of the Republic of Tuva. Bulletin of the Tuva State University. No. 3 Technical and Physical and Mathematical Sciences. 2022;94(2):14–20. (In Russ.) http://doi.org/10.24411/2221-0458-2022-94-14-20

13. El-Habashy Sh, Alqahtani FK, Mekawy M. Identification of 4D-BIM Barriers in Offshore Construction Projects Using Fuzzy Structural Equation Modeling. Buildings. 2023;13(6):1512. http://doi.org/10.3390/buildings13061512


Review

For citations:


Kryukov K.M. Assessing the Benefits and Challenges of Implementing 4D Modeling in Construction. Modern Trends in Construction, Urban and Territorial Planning. 2025;4(2):75-84. https://doi.org/10.23947/2949-1835-2025-4-2-75-84. EDN: DTRROH