Analysis of Control of Construction Timing Taking into Account the Early Warning System of Missed Deadlines

https://doi.org/10.23947/2949-1835-2025-4-4-7-18

EDN: CHJXJH

Abstract

Introduction. The study is dedicated to evaluating the existing methods for monitoring the construction time of residential buildings and substantiating the advantages of the early warning system (EWS). Traditional tools such as schedules and monitoring are insufficiently effective due to their reactivity and inability to identify risks ahead of time. The aim is to demonstrate the transition from reactive management to proactive predicting likely problems [1]. Modernization of traditional methods by integrating digital tools, introducing predictive analytics and using hybrid management methodologies transforms time control from simple tracking into proactive projection becoming an important competitive edge, allowing the construction industry to effectively deal with challenges and achieve goals with a maximum accuracy.

Materials and Methods. The object of the study is a construction time management system that includes planning, monitoring, and response methods. The major drawbacks of the traditional approach are delayed identification of problems as these methods mainly record problems as they emerge. Assessments are biased and holistic information environment is lacking.

Research Results. As part of the study, the author is expected to design a unique system of EWS indicators adapted to the realities of the Russian construction conditions, a methodology for integrating predicative analytics into the BIM environment, as well as an economic and mathematical model for calculating the effect of EWS implementation. These solutions will reduce the number of missed deadlines by 20–30%, automatically detect risks a week or a week and a half before they emerge, and achieve up to a 95% accuracy in predicting project completion.

Discussion and Conclusion. The proposed measures have a high practical value as they contribute to reducing developers’ financial and reputational costs, implementing legislative norms and increasing amount of trust among those involved in the market. Integration of modern technologies, use of predictive models and flexible management approaches transform timing control from passive monitoring into active prevention of possible disruptions. It is assumed that the implemented method will provide a reduction in the number of cases of missed deadline by 20–30%, and will allow early detection of possible threats prior to the impact of negative consequences improving the quality of project time frame assessment.

About the Authors

N. V. Rozantseva
Saint Petersburg State University of Architecture and Civil Engineering
Россия

Nadezhda V. Rozantseva, Cand.Sci, (Eng.), Associate Professor of the Department of Construction Organization

4 2nd Krasnoarmeyskaya Str., Saint Petersburg, 190005



N. A. Baburin
Saint Petersburg State University of Architecture and Civil Engineering
Россия

Nikita A. Baburin, Master's Student at the Department of Construction Organization

4 2nd Krasnoarmeyskaya St., Saint Petersburg, 190005



References

1. Zotova KA, Lankina YuA, Melnikova NS Problems of Introducing Information Modeling Methods in Russia. Ogarev-Online. 2023;7(192):1–6. (In Russ.) URL: https://cyberleninka.ru/article/n/problemy-vnedreniya-tehnologiy-informatsionnogo-modelirovaniya-v-rossii/viewer (accessed: 13.10.2025)

2. Shafranova АА, Koklugina LА, Koklugin AV Ways of Calculating the Period of Building Process Considering External Factors. News of the Kazan State University of Architecture and Engineering. 2013;4(26):262–267. (In Russ.) URL: https://cyberleninka.ru/article/n/varianty-opredeleniya-prodolzhitelnosti-stroitelstva-na-osnovevliyaniya-vneshnih-faktorov/viewer (accessed: 13.10.2025)

3. Topchiy DV, Tokarskiy AYa The Concept of Quality Control of the Organization of Construction Processes during Construction Supervision through the Use of Information Technology. The Eurasian Scientific Journal. 2019;11(3). (In Russ.) URL: https://esj.today/PDF/52SAVN319.pdf (accessed: 13.10.2025)

4. Bolotin SA, Al-Janabi MA, Bohan KhA Forecasting of the Construction Completion Based on the Modeling of Nonlinear Dependence on Delays of Individual Works. Bulletin of Civil Engineers. 2022;2(91):83–90. (In Russ.) https://doi.org/10.23968/1999-5571-2022-19-2-83-90

5. Kotovskaya MA Development of Calendar Planning for Online Construction Based on the Critical Chain Method and Statistical Modeling. Dissertation for the Degree of Candidate of Science in Engineering. St. Petersburg: SPBGASU; 2015. (In Russ.)

6. Mikhalchenko OYu, Lapidus AA, Faizullin IE Bifurcation Processes in Managing the Timing and Costs of Construction Projects. The Eurasian Scientific Journal. 2024;16(6). URL: https://esj.today/PDF/34SAVN624.pdf (accessed: 13.10.2025).

7. Lapidus AA, Faizullin IE, Mikhalchenko OYu Method for Forming Organizational and Technical Solutions during the Construction of Permanent Construction Projects. Construction Production. 2024;4:3–8.

8. Tyutina AD, Galkin MV Application of Artificial Intelligence in Construction and Architecture. Eurasian Scientific Association. 2021;3–6(73):481–483. (In Russ.)

9. Simankina TL Improving the Calendar Planning of Resource-SavingFlows Taking into Account the Additivity of the Labor Intensity of Performers. Dissertation for the degree of Candidate Science in Engineering. St. Petersburg: Saint Petersburg State University of Architecture and Civil Engineering; 2007. 157 p.

10. Mikhalchenko OYu, Lapidus AA, Tkach AA Adaptive Models of Construction System Management. The Eurasian Scientific Journal. 2025;17(1). (In Russ.) URL: https://esj.today/PDF/29SAVN125.pdf (accessed: 13.10.2025)

11. Zakharova MYu Overview of the Key Aspects of BIM at the Stages of the Life Cycle of a Construction Facility. Proceedings of the International Scientific and Technical Conference of Young Scientists of BSTU named after V.G. Shukhov. 2022. P. 79–83.

12. Leach L.P. Critical Chain Project Management. Third Edition. Artech House; 2014. 345 p.


Review

For citations:


Rozantseva N.V., Baburin N.A. Analysis of Control of Construction Timing Taking into Account the Early Warning System of Missed Deadlines. Modern Trends in Construction, Urban and Territorial Planning. 2025;4(4):7-18. https://doi.org/10.23947/2949-1835-2025-4-4-7-18. EDN: CHJXJH

Views: 53

JATS XML


Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 License.


ISSN 2949-1835 (Online)