Analysis of Timing Results during Continuous Concreting of a Massive Foundation Slab

https://doi.org/10.23947/2949-1835-2026-5-1-79-88

Abstract

Introduction. Risk assessment of early cracking during hardening of massive monolithic reinforced concrete foundation slabs due to temperature gradients enhances the relevance of studies of a host of factors related to a concreting technology given the technical capabilities of workers and suppliers of concrete mixtures, as well as weather conditions. While developing technological regulations for concreting with a calculation of the thermal stress state in the early period in order to reduce and control heat dissipation, studies in the field of assignment and regulation of time parameters of the process of forming the body of the foundation slab taking into account the prescription features of concrete mixtures and weather conditions are relevant. The aim of the study is to obtain new data for calculating the time parameters of concreting massive structures using concrete pumps with technical characteristics that are not available in the regulatory framework.

Materials and Methods. The paper presents the results of timing the process parameters of continuous concreting of a massive foundation slab with a volume of 1642 m3 in 13.6 h. The numerical values of the concrete mixture pumping speed, maneuvering time of concrete mixer trucks as well as the coefficients of transition from technical to operational performance of concrete pump trucks with a technical capacity of 170 and 180 m3/h are obtained. The use of concrete pumps with such a capacity at an actual unloading speed of concrete mixer trucks of up to 2.3 m3/min ensures an actual pumping performance coefficient of up to 0.81, which basically corresponds to normal operation.

Research Results. The values of the concrete pump utilization coefficient over a time period ranging from 0.478 to 0.841 with an average value of ≈ 0.66 were obtained. The actual average productivity of one concrete pump during the concreting period was ≈ 61 m3/h.

Discussion and Conclusion. With a distance from the concrete pump truck to the concrete mixer truck waiting area within 25–50 m, the maneuvering time does not depend greatly on the distance, according to 69 measurements, it is no more than 5.76 min with a reliability of 0.95 and is identified by the convenience of an area for maneuvering concrete mixer and access roads. The results can be used in developing process regulations for continuous concreting of similar massive structures.

About the Authors

G. V. Nesvetaev
Don State Technical University
Russian Federation

Grigory V. Nesvetaev, Dr.Sc. (Eng.), Professor, Professor of the Department of Construction Production Technology

1 Gagarin Square, Rostov-on-Don, 344003



Ju. I. Koryanova
Don State Technical University
Russian Federation

Julia I. Koryanova, Cand.Sci. (Eng.), Associate Professor, Associate Professor of the Department of Construction Production Technology

1 Gagarin Square, Rostov-on-Don, 344003



V. V. Shut
IE "Shut Vladimir Valeryevich"
Russian Federation

Vladimir V. Shut, Head of IE "Shut Vladimir Valeryevich"

Apartment 1, 3 Yagodnaya Str., Vodopadny, Aksaiskiy district, Rostov region, 346715



References

1. Shcherbakov NA, Dvoenko OV, Aristarkhov VA, Fedyaev VD, Khalikov RV Tactical Specific of Extinguishing Fires in High-Rise Buildings. Fires and Emergencies: Prevention, Elimination. 2023;2:33–43. (In Russ.) https://doi.org/10.25257/FE.2023.2.33-43

2. Shpilevskaya NL, Shvedov AP Features of the Construction of Massive Foundations Taking into Account Various Factors Affecting the Continuous Production of Works. Collection of Scientific Papers of the International Scientific and Practical Conference Dedicated to the 50th Anniversary of the Polotsk State University. Actual Problems of Architecture of the Belarusian Dvina and Adjacent Regions. Novopolotsk: Educational Institution “Polotsk State University”; 2018. P. 238–244. (In Russ.)

3. Kaprielov SS, Sheinfeld AV, Chilin IA Optimization of Concrete Technology Parameters to Ensure Thermal Crack Resistance of Massive Foundations. Construction Materials Russia. 2022;10:41–51. (In Russ.) https://doi.org/10.31659/0585-430X-2022-807-10-41-51

4. Kondratieva TN, Tyurina VS, Chepurnenko AS Predicting the Risk of Early Cracking in Massive Monolithic Foundation Slabs Using Artificial Intelligence Algorithms. Construction Materials and Products. 2025;8(1):6. http://dx.doi.org/10.58224/2618-7183-2025-8-1-6

5. Tyurina VS, Chepurnenko AS, Akopyan VF Prediction of Thermal Cracking During Construction of Massive Monolithic Structures. Applied Sciences. 2025;15(3):1499. https://doi.org/10.3390/app15031499

6. Tyurina VS, Chepurnenko AS, Akopyan VF Methodology for Determining True Temperature Stresses during the Construction of Massive Monolithic Reinforced Concrete Structures. Construction Materials and Products. 2024;7(3):5. https://doi.org/10.58224/2618-7183-2024-7-3-5

7. Travush VI, Nikiforov SV Technology of Concreting Massive Structures of the Foundations of the Lakhta Center Multifunctional Complex. Building and Reconstruction. 2025;(2):44–55. (In Russ.) https://doi.org/10.33979/2073-7416-2025-118-2-44-55

8. Shpilevskaya NL, Shvedov AP Development of Organizational and Technological Documentation for Concreting Massive Foundation Slabs. Bulletin of the Polotsk State University. Series F. Construction. Applied Science. 2018;8:49–55. (In Russ.) URL: https://elib.psu.by/handle/123456789/22821 (accessed: 31.01.2026)

9. Doladov YI, Doladova IP Resource Saving Technology of Pouring Massive Foundation Slab. Bulletin of SGASU. Urban Construction and Architecture. 2011;2:132–134. (In Russ.) https://doi.org/10.17673/Vestnik.2011.02.29

10. Nesvetaev GV, Koryanova YI, Sukhin DP Some Questions of the Technology of Concreting Massive Foundation Slabs Using Self-Compacting Concrete Mixtures. Engineering Journal of Don. 2022;8(92). (In Russ.) URL: http://www.ivdon.ru/ru/magazine/archive/n8y2022/7870 (accessed: 31.01.2026)

11. Kalinovskaya NN, Osos RF, Kuchuk EV Concreting of the Foundation Slab of the Turbine Unit of the Belarusian NPP Using Self-Compacting Concrete. Concrete Technologies. 2017;3–4:15–19. (In Russ.) URL: https://polyplasthim.by/wp-content/uploads/2017/09/Betonirovanie-fundamentnoj-plity-turboagregata-Belorusskoj-AES-s-primeneniem-samouplotnyayushhegosya-betona.-Tehnologiya-betonov.pdf (accessed: 31.01.2026)

12. Kaprielov SS, Sheynfeld AV, Al-Omais D, Zaitsev AS Experience in Production of High-Strength Concrete Used in Construction of High-Rise Complex "OKO" in MIBC "Moscow-City". Industrial and Civil Engineering. 2017;3:53–57. (In Russ.) URL: http://pgs1923.ru/archiv/2018/01/02.pdf (accessed: 31.01.2026)

13. Nesvetaev GV, Koryanova YI, Sukhin DP About Defining Pouring Parameters Massive Flat Foundation Slabs. Engineering Journal of Don. 2023;8(104). (In Russ.) URL: http://www.ivdon.ru/ru/magazine/archive/n8y2023/8626 (accessed: 31.01.2026)

14. Komarinsky MV, Chervova NA Transport of Concrete Mix during Construction of Unique Buildings and Structures. Construction of Unique Buildings and Structures. 2015;1(28):6–7. (In Russ.) URL: https://unistroy.spbstu.ru/userfiles/files/2015/1(28)/1_chervova_28.pdf (accessed: 31.01.2026)

15. Komarinsky MV A Productivity of Reciprocating Concrete Pump. Construction of Unique Buildings and Structures. 2013;6(11):43–49. (In Russ.) URL: https://unistroy.spbstu.ru/userfiles/files/2013/6(11)/6_komarinskij_11.pdf (accessed: 31.01.2026)

16. Velikanov NL, Naumov VA, Koryagin SI Definition of Performance Piston Concrete Pump. Technical and Technological Problems of the Service. 2018;2(44):8–11. (In Russ.) URL: https://sciup.org/opredelenie-proizvoditelnosti-porshnevogo-betononasosa-148186434 (accessed: 31.01.2026)

17. Travush VI, Shakhvorostov AI Concreting the Lower Slab of the Box Foundation of the Tower of the Lakhta Center Complex. High-Rise Buildings. 2015;1:92–101. (In Russ.) URL: http://old.inforceproject.ru/media/article20.pdf (accessed: 31.01.2026)


Review

For citations:


Nesvetaev G.V., Koryanova J.I., Shut V.V. Analysis of Timing Results during Continuous Concreting of a Massive Foundation Slab. Modern Trends in Construction, Urban and Territorial Planning. 2026;5(1):79-88. https://doi.org/10.23947/2949-1835-2026-5-1-79-88

Views: 210

JATS XML


Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 License.


ISSN 2949-1835 (Online)